Forward supply

Housing supply pipeline

20,496 units across 192 licensed developments with a permit still running in Perak. Heavy forward supply in an area tends to cap resale prices, so this is the counterweight to a rising median.

Units by permit expiry quarter

Permit expiry is the only forward date the register carries. A developer must complete and hand over within that window, so it reads as a delivery deadline rather than a launch date.

2k
2026 Q319 proj
3k
2026 Q430 proj
5k
2027 Q147 proj
4k
2027 Q224 proj
3k
2027 Q321 proj
2k
2027 Q415 proj
965
2028 Q115 proj
583
2028 Q212 proj
391
2028 Q38 proj
1k
2029 Q31 proj

By build status

StatusUnitsProjectsShare of units
Lancar12,15211859%
Siap Dengan CCC3,6853318%
Belum Mula2,0441210%
Sakit1,767169%
Lewat831124%
Permit Telah Dibatalkan1710%

Permit windows, not launch dates. A permit expiring in a quarter means delivery is contracted by then, not that units go on sale then. Projects marked Sakit are recorded as distressed by KPKT and may not deliver at all.