Forward supply
Housing supply pipeline
10,644 units across 143 licensed developments with a permit still running in Kedah. Heavy forward supply in an area tends to cap resale prices, so this is the counterweight to a rising median.
All statesSelangorJohorPerakKuala LumpurPenangNegeri SembilanKedahMelakaPahangSarawakTerengganuSabahKelantanPerlisPutrajayaLabuan
Units by permit expiry quarter
Permit expiry is the only forward date the register carries. A developer must complete and hand over within that window, so it reads as a delivery deadline rather than a launch date.
1142026 Q32 proj
1k2026 Q423 proj
2k2027 Q124 proj
2k2027 Q221 proj
3k2027 Q326 proj
6462027 Q414 proj
4642028 Q111 proj
1k2028 Q28 proj
7362028 Q312 proj
5172028 Q42 proj
By build status
Lancar6,9919266%
Siap Dengan CCC2,0402319%
Belum Mula953159%
Lewat46674%
Sakit13941%
Permit Telah Dibatalkan3910%
Siap Dengan CFO1610%
Permit windows, not launch dates. A permit expiring in a quarter means delivery is contracted by then, not that units go on sale then. Projects marked Sakit are recorded as distressed by KPKT and may not deliver at all.