Forward supply

Housing supply pipeline

12,332 units across 85 licensed developments with a permit still running in Melaka. Heavy forward supply in an area tends to cap resale prices, so this is the counterweight to a rising median.

Units by permit expiry quarter

Permit expiry is the only forward date the register carries. A developer must complete and hand over within that window, so it reads as a delivery deadline rather than a launch date.

2k
2026 Q311 proj
2k
2026 Q410 proj
3k
2027 Q112 proj
2k
2027 Q216 proj
424
2027 Q38 proj
775
2027 Q49 proj
140
2028 Q14 proj
532
2028 Q25 proj
334
2028 Q34 proj
98
2028 Q41 proj
909
2029 Q13 proj
750
2029 Q32 proj

By build status

StatusUnitsProjectsShare of units
Lancar8,1516466%
Belum Mula1,975916%
Siap Dengan CCC1,734814%
Lewat41523%
Sakit5720%

Permit windows, not launch dates. A permit expiring in a quarter means delivery is contracted by then, not that units go on sale then. Projects marked Sakit are recorded as distressed by KPKT and may not deliver at all.