Forward supply

Housing supply pipeline

128,590 units across 533 licensed developments with a permit still running in Johor. Heavy forward supply in an area tends to cap resale prices, so this is the counterweight to a rising median.

Units by permit expiry quarter

Permit expiry is the only forward date the register carries. A developer must complete and hand over within that window, so it reads as a delivery deadline rather than a launch date.

838
2026 Q312 proj
13k
2026 Q479 proj
14k
2027 Q168 proj
13k
2027 Q285 proj
13k
2027 Q372 proj
4k
2027 Q429 proj
15k
2028 Q147 proj
14k
2028 Q252 proj
18k
2028 Q342 proj
15k
2028 Q423 proj
2k
2029 Q18 proj
3k
2029 Q27 proj
5k
2029 Q39 proj

By build status

Lancar102,87436880%
Belum Mula10,709528%
Siap Dengan CCC8,923807%
Lewat4,731144%
Sakit1,340181%
Permit Telah Dibatalkan1310%

Permit windows, not launch dates. A permit expiring in a quarter means delivery is contracted by then, not that units go on sale then. Projects marked Sakit are recorded as distressed by KPKT and may not deliver at all.