Forward supply

Housing supply pipeline

13,350 units across 103 licensed developments with a permit still running in Negeri Sembilan. Heavy forward supply in an area tends to cap resale prices, so this is the counterweight to a rising median.

Units by permit expiry quarter

Permit expiry is the only forward date the register carries. A developer must complete and hand over within that window, so it reads as a delivery deadline rather than a launch date.

732
2026 Q46 proj
2k
2027 Q122 proj
1k
2027 Q29 proj
3k
2027 Q318 proj
693
2027 Q46 proj
791
2028 Q17 proj
408
2028 Q210 proj
2k
2028 Q311 proj
2k
2028 Q411 proj
2k
2029 Q13 proj

By build status

Lancar11,6258287%
Belum Mula77096%
Lewat62655%
Sakit32972%

Permit windows, not launch dates. A permit expiring in a quarter means delivery is contracted by then, not that units go on sale then. Projects marked Sakit are recorded as distressed by KPKT and may not deliver at all.