Forward supply
Housing supply pipeline
1,920 units across 27 licensed developments with a permit still running in Kelantan. Heavy forward supply in an area tends to cap resale prices, so this is the counterweight to a rising median.
All statesSelangorJohorPerakKuala LumpurPenangNegeri SembilanKedahMelakaPahangSarawakTerengganuSabahKelantanPerlisPutrajayaLabuan
Units by permit expiry quarter
Permit expiry is the only forward date the register carries. A developer must complete and hand over within that window, so it reads as a delivery deadline rather than a launch date.
1712026 Q34 proj
1642026 Q43 proj
6822027 Q14 proj
5022027 Q27 proj
732027 Q35 proj
2622027 Q43 proj
662028 Q11 proj
By build status
StatusUnitsProjectsShare of units
Lancar1,1051558%
Lewat316416%
Sakit313516%
Permit Telah Dibatalkan12416%
Siap Dengan CCC6223%
Permit windows, not launch dates. A permit expiring in a quarter means delivery is contracted by then, not that units go on sale then. Projects marked Sakit are recorded as distressed by KPKT and may not deliver at all.