Housing supply pipeline

5,292 units across 39 licensed developments with a permit still running in Kelantan. Heavy forward supply in an area tends to cap resale prices, so this is the counterweight to a rising median.

Units by permit expiry quarter

Permit expiry is the only forward date the register carries. A developer must complete and hand over within that window, so it reads as a delivery deadline rather than a launch date.

2k
2026 Q42 proj
746
2027 Q15 proj
1k
2027 Q214 proj
392
2027 Q37 proj
262
2027 Q43 proj
252
2028 Q35 proj
68
2028 Q42 proj
361
2029 Q31 proj

By build status

Lancar4,4172683%
Lewat37037%
Belum Mula26755%
Sakit23854%

Permit windows, not launch dates. A permit expiring in a quarter means delivery is contracted by then, not that units go on sale then. Projects marked Sakit are recorded as distressed by KPKT and may not deliver at all.